The work · Selected loss register 2022-2025
Some of the largest and most complex commercial claims in Australia and New Zealand.
Every engagement below was performed for, or alongside, the appointed loss adjuster, or for the insured on the loss adjuster's recommendation.
Large shopping complex · Brisbane QLD · 2022 EAST COAST FLOODS
~45,000m²
A shopping complex inundated in Australia's costliest insured event, more than $6B in claims.
Damage spanned structure, electrical, HVAC, lifts and widespread water and mould impact, and it was one of the largest single-asset losses of the event. We ran a full-time site presence for several weeks immediately after.
Clerk of Works · restoration
Galvanising plant · Sydney NSW · 2024 FIRE
385t @ 450°C
Molten zinc kept live while we restored the plant around it.
Fire destroyed roughly 60% of a hot-dip galvanising plant's roof. Restoration was delivered without disrupting four treatment tanks or the structural kettle holding around 385 tonnes of molten zinc. A high-risk, live industrial environment.
Clerk of Works · contractor claims
Gas transmission pipeline · Regional NSW · 2022 FLOOD
20,000
Customers back on gas, full pipeline repair in about seven weeks.
A flood-induced pipeline failure at a river crossing caused a gas leak and supply outage to around 20,000 customers across regional NSW. Impacts were managed via emergency LNG supply and a temporary pipeline.
Contractor claim assessment
International hotel · Auckland NZ · 2023 AUCKLAND FLOODS
~NZ$2.2B
Hotel's lower floors flooded in a record Auckland deluge.
Record single-day rainfall and flash flooding inundated an international hotel's ground and lower floors. Full-time site presence for several weeks post-event with cost, plant, equipment and materials verification.
Clerk of Works · scope & pricing
University research laboratory · Sydney NSW · 2025 WATER
~$7M
Specialist research equipment protected after a cooling-water escape.
A cooling-water escape from a refrigeration unit impacted the laboratory below, housing four sensitive low-temperature research setups. Engaged by the loss adjuster to coordinate damage assessment and maintain the equipment damage schedule.
Equipment schedule · claim docs
Commercial display building · Regional NSW · 2025 FIRE
DA → handover
Fire-hit display building rebuilt, approvals fast-tracked.
A large-scale fire required complete strip-out and reinstatement, including replacement of fire-affected structural elements. Engaged as project manager: fast-tracked DA and construction certificate, competitive tender, and site oversight to completion.
Project Manager
Bank branch network · Three sites QLD · 2022 FLOODS
6m deep
Groundwater reached six metres deep. Three bank branches fully stripped and reinstated.
Floodwater drove groundwater up to six metres deep through three bank branches, requiring a full strip-out, dry-down and reinstatement at each site. As project manager to the loss adjuster, we validated the stage one (strip and dry-down) and stage two (reinstate as-was) scopes, then ran delivery oversight with monthly progress, variation, programme and budget reporting across all three branches.
Project Manager to LA
Research laboratory · Sydney NSW · 2024 FIRE
Char & soot
Fire residue cleared across building fabric, services and equipment.
A research laboratory fire distributed char and soot throughout the lab, requiring assessment across building fabric, services and electronic equipment. Clerk of Works for off-site equipment restoration and on-site fabric and services restoration.
Clerk of Works